{"id":792,"date":"2026-08-25T18:15:26","date_gmt":"2026-08-25T16:15:26","guid":{"rendered":"https:\/\/tramuntanaprojects.com\/sin-categorizar\/build-house-mallorca\/"},"modified":"2026-10-20T15:29:04","modified_gmt":"2026-10-20T13:29:04","slug":"build-house-mallorca","status":"publish","type":"post","link":"https:\/\/tramuntanaprojects.com\/en\/permits-regulations\/build-house-mallorca\/","title":{"rendered":"Building a house in Mallorca: costs, permits and timeframes"},"content":{"rendered":"\n<p class=\"has-small-font-size wp-block-paragraph\">By the <a href=\"https:\/\/tramuntanaprojects.com\/en\/about-us\/\">Tramuntana Projects team<\/a>.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Building a house in Mallorca means coordinating <strong>plot, design, budget, permits and construction<\/strong>. The physical build usually takes between twelve and eighteen months, but the process starts much earlier and doesn\u2019t end until the home can legally be occupied.<\/p>\n\n\n<ol class=\"tpv-route\" aria-label=\"From studying the plot to handover\"><li><b>01<\/b><strong>Plot<\/strong><span>Check whether it allows the home.<\/span><\/li><li><b>02<\/b><strong>Design and permit<\/strong><span>Define the house and apply for authorisation.<\/span><\/li><li><b>03<\/b><strong>Measurements<\/strong><span>Define scope and budget.<\/span><\/li><li><b>04<\/b><strong>Construction<\/strong><span>Carry out and certify the work.<\/span><\/li><li><b>05<\/b><strong>Handover<\/strong><span>Complete the occupancy documents.<\/span><\/li><\/ol><p>The plot comes first because it shapes the design, cost and permits. Some preparation phases can overlap.<\/p>\n\n\n<p class=\"wp-block-paragraph\"><strong>Go straight to:<\/strong> <a href=\"#parcela\">plot<\/a> \u00b7 <a href=\"#suelo-rustico\">rural land<\/a> \u00b7 <a href=\"#costes\">costs<\/a> \u00b7 <a href=\"#permisos\">documents and permits<\/a> \u00b7 <a href=\"#plazos\">timeframes<\/a> \u00b7 <a href=\"#sobrecostes\">budget and overruns<\/a> \u00b7 <a href=\"#preguntas-frecuentes\">FAQ<\/a>.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"parcela\">How do you know whether a plot in Mallorca can be built on?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">The answer isn\u2019t just in the Land Registry (Catastro). Before considering a plot viable, we check that planning rules allow residential use, how much can be built and whether the land meets the conditions to obtain a permit.<\/p>\n\n\n\n<style>\n.post-116 .tpv-parcela{display:grid;grid-template-columns:minmax(0,.85fr) minmax(0,1.15fr);gap:clamp(22px,4vw,38px);align-items:start;margin:2rem 0;color:#1D1D1B}\n.post-116 .tpv-parcela .tpv-map{min-width:0;margin:0;padding:0;background:#E6E4DF}\n.post-116 .tpv-parcela .tpv-map svg{display:block;width:100%;height:auto;overflow:visible}\n.post-116 .tpv-parcela .tpv-map figcaption{margin:0;padding:0 20px 20px;font-size:.8rem;line-height:1.5;color:#1D1D1B}\n.post-116 .tpv-parcela .tpv-list{list-style:none;margin:0;padding:0;counter-reset:none}\n.post-116 .tpv-parcela .tpv-list>li{display:grid;grid-template-columns:28px minmax(0,1fr);gap:12px;margin:0;padding:0 0 18px;border:0;list-style:none}\n.post-116 .tpv-parcela .tpv-list>li+li{padding-top:18px;border-top:1px solid rgba(29,29,27,.18)}\n.post-116 .tpv-parcela .tpv-list>li:last-child{padding-bottom:0}\n.post-116 .tpv-parcela .tpv-key{display:flex;align-items:center;justify-content:center;width:28px;height:28px;background:#7FA8AE;color:#1D1D1B;border-radius:50%;font-size:.8rem;font-weight:600;line-height:1}\n.post-116 .tpv-parcela .tpv-list h3{margin:0 0 7px;padding:0;font-size:1.02rem;font-weight:500;line-height:1.35;color:#1D1D1B}\n.post-116 .tpv-parcela .tpv-list p{margin:0;padding:0;font-size:.94rem;line-height:1.6;color:#1D1D1B}\n@media(max-width:680px){.post-116 .tpv-parcela{grid-template-columns:minmax(0,1fr);gap:24px}.post-116 .tpv-parcela .tpv-map svg{max-height:320px}.post-116 .tpv-parcela .tpv-list>li{grid-template-columns:28px minmax(0,1fr);gap:12px}}\n<\/style>\n<div class=\"tpv-parcela\">\n  <figure class=\"tpv-map\">\n    <svg xmlns=\"http:\/\/www.w3.org\/2000\/svg\" viewBox=\"0 0 440 410\" aria-hidden=\"true\" focusable=\"false\">\n      <path d=\"M64 86 343 62 382 299 91 335Z\" fill=\"#F4F3EF\"\/>\n      <path d=\"M183 324 91 335 64 86 343 62 382 299 240 317\" fill=\"none\" stroke=\"#1D1D1B\" stroke-width=\"2.5\" stroke-linejoin=\"round\"\/>\n      <path d=\"M20 369H420\" fill=\"none\" stroke=\"#7FA8AE\" stroke-width=\"27\" opacity=\".25\"\/>\n      <path d=\"M20 369H420\" fill=\"none\" stroke=\"#1D1D1B\" stroke-width=\"1.5\" stroke-dasharray=\"8 8\" opacity=\".5\"\/>\n      <path d=\"M216 368 212 323\" fill=\"none\" stroke=\"#7FA8AE\" stroke-width=\"11\"\/>\n      <path d=\"m202 329 10-16 12 14\" fill=\"none\" stroke=\"#1D1D1B\" stroke-width=\"2\" stroke-linecap=\"round\" stroke-linejoin=\"round\"\/>\n      <path d=\"M75 117 78 153M72 108 76 99\" fill=\"none\" stroke=\"#7FA8AE\" stroke-width=\"5\" stroke-linecap=\"round\"\/>\n      <g fill=\"#7FA8AE\" stroke=\"#F4F3EF\" stroke-width=\"4\">\n        <circle cx=\"145\" cy=\"139\" r=\"19\"\/>\n        <circle cx=\"311\" cy=\"117\" r=\"19\"\/>\n        <circle cx=\"302\" cy=\"259\" r=\"19\"\/>\n        <circle cx=\"204\" cy=\"289\" r=\"19\"\/>\n      <\/g>\n      <g fill=\"#1D1D1B\" font-family=\"Arial,sans-serif\" font-size=\"16\" font-weight=\"600\" text-anchor=\"middle\">\n        <text x=\"145\" y=\"145\">1<\/text>\n        <text x=\"311\" y=\"123\">2<\/text>\n        <text x=\"302\" y=\"265\">3<\/text>\n        <text x=\"204\" y=\"295\">4<\/text>\n      <\/g>\n    <\/svg>\n    <figcaption>Indicative diagram of boundaries and an access point; it doesn\u2019t represent a real plot.<\/figcaption>\n  <\/figure>\n  <ol class=\"tpv-list\" aria-label=\"Four checks before buying a plot\">\n    <li>\n      <span class=\"tpv-key\" aria-hidden=\"true\">1<\/span>\n      <div>\n        <h3>Planning rules and planning certificate<\/h3>\n        <p>For that specific plot, check the permitted use, buildable area, site coverage, heights and setbacks. If it\u2019s urban land, also verify that it qualifies as a building plot (solar) and any outstanding obligations for infrastructure or land transfers.<\/p>\n      <\/div>\n    <\/li>\n    <li>\n      <span class=\"tpv-key\" aria-hidden=\"true\">2<\/span>\n      <div>\n        <h3>Property Registry and Catastro<\/h3>\n        <p>Cross-check area, boundaries and ownership between the documents. Also review subdivisions and the buildings recorded. If you find discrepancies, clarify them before buying and before treating the plot information as valid.<\/p>\n      <\/div>\n    <\/li>\n    <li>\n      <span class=\"tpv-key\" aria-hidden=\"true\">3<\/span>\n      <div>\n        <h3>Constraints<\/h3>\n        <p>Check whether coastal law, roads, flood risk, heritage or protected areas apply. These constraints may require reports, limit the planned work or prevent it. Establish what affects that plot rather than assuming it from what you see around it.<\/p>\n      <\/div>\n    <\/li>\n    <li>\n      <span class=\"tpv-key\" aria-hidden=\"true\">4<\/span>\n      <div>\n        <h3>Access, services and ground<\/h3>\n        <p>Check access for lorries and a crane, as well as how water, drainage and electricity will be provided. The slope and the presence of rock can affect excavation and structure.<\/p>\n      <\/div>\n    <\/li>\n  <\/ol>\n<\/div>\n\n\n\n\n<div class=\"note t\"><b class=\"rotulo\">Before buying: first review of the plot<\/b><b>What we need:<\/b> cadastral reference, land registry extract (nota simple), municipality, location or plan and photos of the access.<br><b>What we\u2019ll tell you:<\/b> whether we see an initial blocker, what still needs checking and whether it makes sense to proceed before signing. It doesn\u2019t replace the planning study or ground tests.<\/div>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"suelo-rustico\">Can a house be built on rural land in Mallorca?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Short answer:<\/strong> only if planning rules allow a detached home, the property meets the minimum area required in that zone and no constraint prevents it. Having 14,000 m\u00b2 does not, on its own, confirm the plot can be built on.<\/p>\n\n\n\n<div class=\"tbw\"><table class=\"tb\">\n<thead><tr><th>What we check<\/th><th>What it means for your plot<\/th><\/tr><\/thead>\n<tbody>\n<tr><td><b>Land category<\/b><\/td><td>It must allow a detached home. If residential use is prohibited, a new house can\u2019t be built.<\/td><\/tr>\n<tr><td><b>Minimum area<\/b><\/td><td>14,000 m\u00b2 is common but not universal: some areas require 50,000 m\u00b2. If the property doesn\u2019t reach the applicable minimum, it isn\u2019t viable.<\/td><\/tr>\n<tr><td><b>Constraints and history<\/b><\/td><td>Even if it meets the two previous conditions, protections, subdivisions, existing buildings or sector-specific reports can limit or prevent the project.<\/td><\/tr>\n<\/tbody>\n<\/table><\/div>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Conclusion:<\/strong> the property can only be considered potentially viable when it passes all three checks. From there, the home still has to be defined and the corresponding authorisations obtained.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"costes\">How much does it cost to build a house in Mallorca in 2026?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">It depends on the specification, the plot and what the calculation includes. These indicative construction references help size a first idea; they don\u2019t represent the final contract price. The specific proposal must identify the measured area, taxes and included items. The levels only make sense if services, windows and doors, finishes, fittings and bespoke work are defined; without a specification document they\u2019re just labels.<\/p>\n\n\n\n<div class=\"tbw\"><table class=\"tb\">\n<thead><tr><th>Specification level<\/th><th>Construction guide<\/th><th>Example for 150 m\u00b2<\/th><\/tr><\/thead>\n<tbody>\n<tr><td><b>Standard<\/b><\/td><td>\u20ac2,300\u20132,800\/m\u00b2<\/td><td class=\"r\">\u20ac345,000\u2013420,000<\/td><\/tr>\n<tr><td><b>Mid-range<\/b><\/td><td>\u20ac2,800\u20133,500\/m\u00b2<\/td><td class=\"r\">\u20ac420,000\u2013525,000<\/td><\/tr>\n<tr><td><b>High<\/b><\/td><td>\u20ac3,500\u20134,500\/m\u00b2<\/td><td class=\"r\">\u20ac525,000\u2013675,000<\/td><\/tr>\n<tr><td><b>Luxury villa<\/b><\/td><td>From \u20ac4,500\/m\u00b2<\/td><td class=\"r\">From \u20ac675,000<\/td><\/tr>\n<\/tbody>\n<\/table><\/div>\n\n\n\n<p class=\"wp-block-paragraph\">For a 150 m\u00b2 mid-range house, multiplying the area by the \u20ac2,800\u20133,500\/m\u00b2 reference gives <strong>\u20ac420,000\u2013525,000 as a construction guide<\/strong>. We don\u2019t add a generic 28%: land, taxes, fees, permits and additional items must be assessed separately according to the engagement.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Also check pool, walls, garden, fittings and utility connections: don\u2019t assume they\u2019re included if they don\u2019t appear in the measurements. Tax treatment and fees are specified in each proposal, not deduced from the price per metre.<\/p><div class=\"note t\"><b class=\"rotulo\">Want to compare your own scenario?<\/b>The <a href=\"https:\/\/tramuntanaprojects.com\/en\/renovation-costs-mallorca\/#calc\">new-build estimator<\/a> lets you adjust floor area and finish level to compare a first estimate and request a quote for your project. It\u2019s an initial guide, not an offer.<\/div>\n\n\n\n<div class=\"note t\"><b class=\"rotulo\">When it stops being an estimate<\/b> With square metres and finish level we can give a range. With a topographic survey, geotechnical study, construction design and measurements we can compare offers. If an item isn\u2019t defined yet, we leave it as an estimate or exclusion; we don\u2019t disguise it as a fixed price.<\/div>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"permisos\">What documents and permits do you need to build a house in Mallorca?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Permits to build a house in Mallorca aren\u2019t resolved with a single authorisation. For a new home you need a technical design, a planning permit, a construction design and notice of start of works; at the end, a completion certificate and an occupancy licence or the equivalent document. <strong>They aren\u2019t seven permits:<\/strong> they\u2019re different documents and each unlocks a phase.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>These are the documents you\u2019ll need, in order:<\/strong><\/p>\n\n\n\n<div class=\"acc\">\n<details open>\n<summary>01 \u00b7 Basic design (proyecto b\u00e1sico)<\/summary>\n<div class=\"a\"><p><strong>Prepared by the architect.<\/strong> It defines the home and demonstrates its planning compliance in enough detail to apply for the permit. On its own it doesn\u2019t allow construction to start.<\/p><\/div>\n<\/details>\n<details>\n<summary>02 \u00b7 Sector-specific reports and authorisations<\/summary>\n<div class=\"a\"><p><strong>Issued by the relevant authorities, only where applicable.<\/strong> They review constraints relating to roads, coast, heritage, water resources or rural land that the town council can\u2019t resolve on its own.<\/p><\/div>\n<\/details>\n<details>\n<summary>03 \u00b7 Building permit<\/summary>\n<div class=\"a\"><p><strong>Granted by the town council.<\/strong> It authorises the home in line with the design and the approved conditions. Receiving it doesn\u2019t necessarily mean machinery can move in that same day.<\/p><\/div>\n<\/details>\n<details>\n<summary>04 \u00b7 Construction design (proyecto de ejecuci\u00f3n)<\/summary>\n<div class=\"a\"><p><strong>Prepared by the architect.<\/strong> It develops structure, services, materials, details and measurements. It\u2019s the document used to compare quotes and build the house.<\/p><\/div>\n<\/details>\n<details>\n<summary>05 \u00b7 Notice of start of works<\/summary>\n<div class=\"a\"><p><strong>Submitted by the owner or their representative.<\/strong> It informs the town council of the planned start date. It must be filed at least ten days in advance and doesn\u2019t replace the permit.<\/p><\/div>\n<\/details>\n<details>\n<summary>06 \u00b7 Completion certificate<\/summary>\n<div class=\"a\"><p><strong>Signed by the site supervision team.<\/strong> It certifies that the home is finished and matches the approved design, including any authorised changes.<\/p><\/div>\n<\/details>\n<details>\n<summary>07 \u00b7 Occupancy or first-use licence<\/summary>\n<div class=\"a\"><p><strong>Requested by the owner and decided by the town council.<\/strong> It verifies that the home matches the earlier permit and authorises its use, or is replaced by the equivalent document provided for the case.<\/p><\/div>\n<\/details>\n<\/div>\n\n\n\n<p class=\"wp-block-paragraph\">If the permit was obtained with the basic design only, the construction design must be submitted within nine months, and the town council has one month to check that it develops what was approved. The key idea is simple: paying fees, filing documents or receiving a quote <strong>doesn\u2019t mean construction can start yet<\/strong>.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Before filing the design, we check which reports are needed and who must provide them. Then we use the same documentation to quote, build and certify. That way we avoid the council reviewing one version of the design while construction follows another. This control is also part of our <a href=\"https:\/\/tramuntanaprojects.com\/en\/service\/technical-management-permits-mallorca\/\">project and site management<\/a>.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1440\" height=\"960\" src=\"https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/planificacion-obra-nueva-mallorca-tramuntana.webp\" alt=\"Reviewing plans and measurements to plan a build\" class=\"wp-image-119\" srcset=\"https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/planificacion-obra-nueva-mallorca-tramuntana.webp 1440w, https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/planificacion-obra-nueva-mallorca-tramuntana-300x200.webp 300w, https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/planificacion-obra-nueva-mallorca-tramuntana-1024x683.webp 1024w, https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/planificacion-obra-nueva-mallorca-tramuntana-768x512.webp 768w\" sizes=\"auto, (max-width: 1440px) 100vw, 1440px\" \/><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"plazos\">How long does it really take to build a house in Mallorca?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">The physical build usually takes <strong>between twelve and eighteen months<\/strong>. The whole process usually exceeds two years because feasibility, design and permit come first; on rural land or with sector-specific reports it can exceed three.<\/p>\n\n\n\n<ul class=\"fic\">\n<li><span>Feasibility, studies and design<\/span><span>3\u20137 months, indicative<\/span><\/li>\n<li><span>Permit process<\/span><span>6\u201318 months or more<\/span><\/li>\n<li><span>Construction of the home<\/span><span>12\u201318 months typically<\/span><\/li>\n<li><span>First occupancy and close-out<\/span><span>Weeks or months<\/span><\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">Timeframes don\u2019t always add up mechanically. While the permit is being processed, measurements can be finalised, offers compared and supplies planned. What you can\u2019t do is start construction. Preparing that phase well avoids losing more months when the authorisation arrives.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"sobrecostes\">What should the quote include to avoid cost overruns?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">A quote usually goes up because items are missing or have been left as provisional sums: excavation without a geotechnical study, utility connections not located, pool and walls left out of the calculation, or finishes not yet chosen. The problem isn\u2019t just the price per metre, but everything that price wasn\u2019t counting.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1440\" height=\"960\" src=\"https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/cimentacion-casa-mallorca-tramuntana.webp\" alt=\"Detail of the foundation reinforcement of a house\" class=\"wp-image-120\" srcset=\"https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/cimentacion-casa-mallorca-tramuntana.webp 1440w, https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/cimentacion-casa-mallorca-tramuntana-300x200.webp 300w, https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/cimentacion-casa-mallorca-tramuntana-1024x683.webp 1024w, https:\/\/tramuntanaprojects.com\/wp-content\/uploads\/2026\/08\/cimentacion-casa-mallorca-tramuntana-768x512.webp 768w\" sizes=\"auto, (max-width: 1440px) 100vw, 1440px\" \/><\/figure>\n\n\n\n<section class=\"tpv-budget\"><h3>Before signing: four checks on the quote<\/h3><dl><div><dt>Ground<\/dt><dd>Topographic survey, geotechnical study, excavation, soil removal and foundations. If subsoil information is missing, identify why and the provisional item.<\/dd><\/div><div><dt>Access and connections<\/dt><dd>Lorries, crane, pumping, material storage and water, drainage and electricity connections. Define who carries out each connection and how far the price goes.<\/dd><\/div><div><dt>Outdoor areas<\/dt><dd>Pool, terraces, walls, fences and garden: measured or explicitly excluded, with a separate allowance.<\/dd><\/div><div><dt>Changes<\/dt><dd>Exclusions and provisional sums visible. Every change is priced and approved in writing before it\u2019s carried out, with its effect on price and timeframe.<\/dd><\/div><\/dl><p><strong>The rule:<\/strong> anything not measured is marked provisional; anything not included, as an exclusion.<\/p><\/section>\n\n\n\n<p class=\"wp-block-paragraph\">To compare offers, we make everyone price the same measurements and exclusions. During construction we certify by line item, and every change is approved with its cost and effect on the schedule. We also recommend looking at <a href=\"https:\/\/tramuntanaprojects.com\/en\/projects\/\">completed projects in Mallorca<\/a>: a finished build explains the quality of execution better than a render.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"preguntas-frecuentes\">Frequently asked questions about building a house in Mallorca<\/h2>\n\n\n\n<div class=\"acc\">\n<details open>\n<summary>Is it wise to buy the plot before studying whether it can be built on?<\/summary>\n<div class=\"a\"><p>It isn\u2019t wise to sign without reviewing planning rules, registry and cadastral status, access, services and constraints. A land registry extract and the cadastral reference let the analysis start, but don\u2019t replace the planning check or the technical study of the ground. We\u2019d rather spot a blocker before the purchase turns it into a problem.<\/p><\/div>\n<\/details>\n<details>\n<summary>Is the price per square metre calculated on usable or built area?<\/summary>\n<div class=\"a\"><p>The quote must specify which area it measures: <strong>usable or built<\/strong>. They aren\u2019t interchangeable. The calculations in this article are indicative examples; before applying them to a build, the measurement must be fixed, as well as whether the proposal includes VAT, fees, permit, pool, walls, garden and connections. If two quotes start from different areas or inclusions, the price per metre doesn\u2019t allow them to be compared.<\/p><\/div>\n<\/details>\n<details>\n<summary>How long does the town council take to grant the permit?<\/summary>\n<div class=\"a\"><p>There\u2019s no single timeframe: it depends on the municipality, its workload and whether sector-specific reports or corrections are needed. In practice it can range from several months to over a year. What we can control is submitting a coherent file, anticipating foreseeable reports and responding together to requests so as not to add avoidable delays.<\/p><\/div>\n<\/details>\n<details>\n<summary>What\u2019s the difference between the basic design and the construction design?<\/summary>\n<div class=\"a\"><p>The basic design defines the home and demonstrates planning compliance; it\u2019s used to apply for the permit. The construction design develops structure, services, materials, details and measurements: it\u2019s the document used to quote and build. Getting the permit with the basic design doesn\u2019t allow skipping the construction design or starting work without completing the prior procedures.<\/p><\/div>\n<\/details>\n<details>\n<summary>Do I need an architect and a technical architect for a new home?<\/summary>\n<div class=\"a\"><p>Yes. The architect prepares the design and directs the work; the technical architect (aparejador) controls the physical construction, quality and certifications. We coordinate that documentation with measurements, purchasing, trades and planning so that the approved design is also the one that\u2019s quoted and built.<\/p><\/div>\n<\/details>\n<details>\n<summary>Does a modular or prefabricated home need a permit?<\/summary>\n<div class=\"a\"><p>Yes, when it\u2019s installed as a permanent home. The system may shorten some manufacturing or assembly work, but it doesn\u2019t remove the planning check: a compatible plot, technical design, permit, site supervision and final documentation are still needed before it can be occupied.<\/p><\/div>\n<\/details>\n<details>\n<summary>Can I change the home after getting the permit?<\/summary>\n<div class=\"a\"><p>Yes, but the change must be reviewed before it\u2019s built. If it alters planning parameters, structure, volume, use or permit conditions, it may require an amended design and a new authorisation. On site we first check the technical, administrative, financial and timing impact; building the change and regularising it afterwards is the riskiest option.<\/p><\/div>\n<\/details>\n<details>\n<summary>What\u2019s the difference between PEM, the contractor\u2019s quote and total investment?<\/summary>\n<div class=\"a\"><p>The PEM is the design\u2019s material construction budget (presupuesto de ejecuci\u00f3n material) and is the basis for certain administrative calculations; it isn\u2019t necessarily the builder\u2019s final offer. The contractor\u2019s quote includes the real valuation of the work and its conditions. Total investment also adds fees, permit, taxes, studies, outdoor works, fittings and contingencies. To know how much money you need, look at that last figure.<\/p><\/div>\n<\/details>\n<\/div>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"siguiente-paso\">Already have a plot or design? Here\u2019s the next step<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">If you\u2019re considering a plot, send us the cadastral reference, the land registry extract, the municipality, the approximate floor area of the home and photos of the access. If you already have a design, add plans, measurements, topographic survey, geotechnical study and the permit status.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">With that information we can tell you what\u2019s clear, what still needs checking and whether it makes sense to ask for prices yet. <a href=\"https:\/\/tramuntanaprojects.com\/en\/contact\/\">Tell us about your project<\/a> and we\u2019ll point you to the specific next step, even if you\u2019re not ready to request a quote yet.<\/p>\n\n\n<style>.post-116 article .content-wysiwyg .tpv-route{display:grid;grid-template-columns:repeat(5,minmax(0,1fr));gap:16px;list-style:none;padding:0;margin:32px 0}.post-116 article .content-wysiwyg .tpv-route li{list-style:none;padding:16px 0 0;margin:0;border-top:2px solid #7fa8ae;position:relative}.post-116 .tpv-route b{display:block;color:#436d73;font-size:14px;margin-bottom:8px}.post-116 .tpv-route strong{display:block;font-size:15px;line-height:1.4}.post-116 .tpv-route span{display:block;font-size:13px;line-height:1.5;margin-top:8px}.post-116 article .content-wysiwyg .tpv-budget{padding:26px 0;margin:30px 0;border-top:2px solid #7fa8ae;border-bottom:1px solid #c9c9c1}.post-116 article .content-wysiwyg .tpv-budget h3{font-size:25px;margin:0 0 22px}.post-116 .tpv-budget dl{margin:0}.post-116 .tpv-budget dl>div{display:grid;grid-template-columns:150px minmax(0,1fr);gap:20px;padding:16px 0;border-top:1px solid #c9c9c1}.post-116 .tpv-budget dt{font-weight:600}.post-116 .tpv-budget dd{margin:0;line-height:1.65}.post-116 article .content-wysiwyg .tpv-budget p{font-size:15px;margin:20px 0 0}.post-116 article .content-wysiwyg .tpv-list h3,.post-116 article .content-wysiwyg .tpv-list p{margin:0}.post-116 article .content-wysiwyg .tpv-list h3{margin-bottom:7px}@media(max-width:680px){.post-116 article .content-wysiwyg .tpv-route{grid-template-columns:1fr;gap:0}.post-116 article .content-wysiwyg .tpv-route li{display:grid;grid-template-columns:36px minmax(0,1fr);gap:4px 12px;border-top:0;border-left:2px solid #7fa8ae;padding:0 0 20px 18px}.post-116 .tpv-route span{grid-column:2;font-size:15px;margin:0}.post-116 .tpv-route b{grid-row:span 2}.post-116 .tpv-budget dl>div{grid-template-columns:1fr;gap:8px}}<\/style>","protected":false},"excerpt":{"rendered":"<p>What to check before buying a plot, how to organise the budget and which permits a new home needs in Mallorca.<\/p>\n","protected":false},"author":1,"featured_media":118,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[47],"tags":[],"class_list":["post-792","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-permits-regulations"],"acf":[],"_links":{"self":[{"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/posts\/792","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/comments?post=792"}],"version-history":[{"count":1,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/posts\/792\/revisions"}],"predecessor-version":[{"id":794,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/posts\/792\/revisions\/794"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/media\/118"}],"wp:attachment":[{"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/media?parent=792"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/categories?post=792"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/tramuntanaprojects.com\/en\/wp-json\/wp\/v2\/tags?post=792"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}